Progress View

The Progress view shows the progress of a job or user operation performed in the CA SymDump views for example, requesting an index list from the server.

The status of the Progress view changes each time a new action or operation is performed, for example when a member in the Protsyms view is double clicked to display a report, the contents in the Progress view changes accordingly.

To manage the statuses of operations displayed in the Progress view

  1. Click the Progress view tab to highlight the view's toolbar.

    Note: If the Progress view is not visible, click Window, Show Views, Progress to display the Progress view.

  2. Use the following icons on the Progress view toolbar to perform the appropriate action:

Icon

Description

Remove All Finished Operations

Removes all the statuses of operations displayed in the Progress view.

The following statuses are shown in the Progress view:

More information:

CA SymDump Views

Set Preferences to Display the Progress View

Remove All Finished Operations from the Progress View